Final sealing works scheduled

FINAL sealing works on local roads have been scheduled in January and February as part of the Upper Yorke Peninsula Regional Road Network Upgrade Program.

 Works will be undertaken during the day between 7am and about 5pm. Temporary speed restrictions will apply but no roads will close.

A 25km/h speed restriction will be in place while workers are on site with other speed restrictions subject to on site conditions.

After care signage (80km/hr speed restrictions) will be in place for about one week after spray seals are completed and before permanent line marking is installed.

Works apply in our area as follows*:

Jan 10-19 from Bute to Kulpara

Jan 11 from Owen to Hamley Bridge

Jan 12 from Balaklava to Mallala

Jan 30 – Feb 3 from Kadina to Paskeville

Feb 5-7 from Paskeville to Kulpara

*Dates may vary as works progress

Read the full story in our online edition: http://plainsproducer.realviewdigital.com